Most hospitality projects that miss an opening date miss it in procurement, not design. This blueprint sets out the lead times, freight times and budget percentages Studio Emanuel plans with in 2026, and how keeping design and procurement in one team keeps them on schedule.
- Imported FF&E: 12–22 weeks from order to delivery (Studio Emanuel project planning)
- Genoa to Miami by container: about 21 days port to port; add 2–3 weeks door to door
- Bespoke joinery 12–20 weeks · upholstery 10–16 · decorative lighting 8–16 · contract furniture 8–14
- Trade net is typically 20–50% below list price; Studio Emanuel bills net + 20%, disclosed
- Activation fee: 5% of phase budget (off-the-shelf) or 10% (custom), credited in full
- Samples for heavy custom upholstery: about 8% of the furniture budget
- Vendor quotes: typically valid 30 days
1. What “the seam” is
The seam is the handoff between the people who design a space and the people who buy for it. When a designer hands drawings to a separate purchasing firm, every substitution, re-quote and missed lead time happens in that gap, and nobody owns the outcome. Studio Emanuel holds both sides under one contract, so the person who specified a chair is the person who places its order and tracks it to the room.
2. Lead times to plan for
Custom FF&E is the longest item on almost every hospitality schedule. Published 2026 planning ranges, before freight and installation:
| Category | Typical lead time |
|---|---|
| Bespoke joinery and casegoods | 12–20 weeks |
| Upholstered furniture | 10–16 weeks |
| Decorative lighting | 8–16 weeks |
| Contract (catalogue) furniture | 8–14 weeks |
| Custom contract furniture, including shipping | 14–18 weeks |
Sources: Zigaflow, Hospitality FF&E Project Management, July 2026; CFS Hospitality, Costs & Lead Times for Commercial Hospitality Furniture.
For imported pieces delivered to Miami, Studio Emanuel plans 12 to 22 weeks from order. Italian freight is planned at about 30 days: the fastest Genoa-to-Miami container services take about 21 days port to port, and booking, customs and delivery usually add two to three weeks.
3. Where the budget goes
A procurement budget is only predictable when the pricing model is. Studio Emanuel’s model, stated plainly:
- Trade net. Hospitality FF&E is bought at trade net, typically 20–50% below list price.
- Net + 20%. The client price is net plus a disclosed 20%. That is the only margin: no vendor rebates or kickbacks, and trade discounts, rebates and freight credits pass to the client.
- Activation fee. 5% of the phase budget for off-the-shelf work, 10% for custom work, credited in full toward the phase.
- Samples. For heavy custom upholstery, carry about 8% of the furniture budget for first samples.
- Trades. Lighting, AV, millwork and installation are passed through at the installers’ quotes, itemised.
For context, HVS reports a 2026 median U.S. hotel development cost of $213,000 per room, and over $1.6 million per room for luxury hotels. FF&E decisions made late are among the most expensive ways to move that number.
4. How managing the seam prevents delays
Order the longest lead first
Custom joinery, upholstery and specialist lighting are ordered first, as soon as their designs are signed off. Plan against the installation window, not the opening date.
One specification, one purchase order
When the designer issues the purchase order, the specification cannot drift between drawing and order. Substitutions are decided by the person who chose the original.
Approve samples before production
Fabric, finish and lighting samples are approved before production starts, so the first full piece is not the first time anyone sees it.
Lock quotes inside their validity
Vendor quotes typically hold for 30 days. Sign-off packages are timed so orders are placed inside that window, before prices or lead times move.
Plan for Miami’s climate and code
Fixed exterior elements in Miami-Dade, such as pergolas and shade structures, fall under the county’s product approval system for the High-Velocity Hurricane Zone, and coastal hardware must resist salt air. Specify approved products early; they are rarely the stock version.
5. A working timeline
| Weeks before install | Milestone |
|---|---|
| 26+ | Concept approved; longest-lead items identified |
| 22–24 | Sign-off package; long-lead orders placed within quote validity |
| 16–20 | Samples approved; standard items ordered |
| 6–8 | Freight booked and consolidated; receiving and storage confirmed |
| 0 | Install, punch list, handover |
Frequently asked questions
How long does custom FF&E take to reach a Miami project?
Plan on 12 to 22 weeks from order to delivery for imported FF&E. Published planning ranges put bespoke joinery at 12–20 weeks, upholstered furniture at 10–16 weeks and decorative lighting at 8–16 weeks, before freight and installation.
How long does freight from Italy to Miami take?
The fastest container services from Genoa to Miami take about 21 days port to port. Door to door, add two to three weeks for booking, customs and delivery. Studio Emanuel plans about 30 days for Italian freight.
What does Studio Emanuel charge for procurement?
Studio Emanuel buys at trade net and bills net plus 20%. The 20% is disclosed and is the only margin: no vendor rebates or kickbacks, and trade discounts, rebates and freight credits pass to the client, with invoices open for review.
What is an activation fee?
An activation fee starts a project phase before renderings and sign-off packages are produced. It is 5% of the phase budget for off-the-shelf work and 10% for custom work, and it is credited in full toward that phase.
What is “the seam” between design and procurement?
The seam is the handoff between the people who design a space and the people who buy for it. When two firms share it, substitutions, re-quotes and missed lead times happen there. Studio Emanuel keeps both under one contract.
How far ahead should I order furniture for a restaurant opening?
Work backwards from the installation window, not the opening date. Order the longest-lead pieces — custom joinery, upholstery and specialist lighting — first, at least 22 weeks before install for imported items.
Sources
- Zigaflow — Hospitality FF&E Project Management for Contract Furniture Specialists (July 2026)
- CFS Hospitality — How to Estimate Costs & Lead Times for Commercial Hospitality Furniture Projects
- Fluent Cargo — Genoa to Miami by container ship
- CargoLinked — Ocean Freight Transit Times by Route (2026)
- HVS — U.S. Hotel Development Cost Survey 2026, via Hospitality Net
- Miami-Dade County — Product Control, Notice of Acceptance (example)
- Studio Emanuel — fee model and planning lead times, 2026